Putnam Community Medical Center

Sanitary Improvements

Location: Palatka, Florida

This project replaced sanitary lines in various locations and was completed in 5 phases. The first phase covered the eastern nursing unit. The next phase addressed work in the Labor and Delivery area. Temporary doors and storage cabinets were also installed. Phase 3 covers work in the soiled utility room and janitor’s closet. The fourth phase addresses work in corridors, break rooms, and restrooms. The fifth phase covers work in the ICU, while some areas were kept operable.